Over thirty road schemes have been delayed as a result of a recent legal challenge affecting the award of a resurfacing contract for the Newry Mourne and Down District Council area.

The Department for Infrastructure had intended to progress these schemes during the current financial year but they will now run into 2022. The DFI have said that the traffic light scheme at Sugar Island/ Water Street in Newry isn't affected and it's still expected that this will be complete in February 2022.

A DFI Spokesperson said "The Department is working at pace to develop and implement a new interim strategy for resurfacing term contracts. The first phase of this, which includes new contracts for the Newry, Mourne and Down Council area, will be going out to tender shortly for award early in the new year. All schemes are subject to ongoing review and reprioritisation."

Delayed Schemes                                                                            

•         B175 Ballylough Rd, Castlewellan                                              
•         A2 Shore Rd, Strangford                                                              
•         C278 Loughinisland Village                                                           
•         B176 Killough Rd, Downpatrick                                                  
•         B175 Drumaroad Hill Road, Ballynahinch                               
•         A28 Abbey Way, Newry                                                                
•         A29 Dundalk Road, Newtownhamilton                                   
•         U6289 Warren Hill, Newry                                                            
•         U6112 Damolly Road, Newry (stage 1)                                    
•         U6112 Damolly Road, Newry (stage 2)                                    
•         U6289 Quay Street, Newry                                                          
•         C227 Castleblayney Road, Newtownhamilton                     
•         A29 Armagh Road, Newtownhamilton                                   
•         B79 Drumalane Road, 
•         C333 Boat Street, Newry                                                              
•         A2 Glassdrumman Road                                                                
•         A25 Camlough Road at St Pauls School, Camlough             
•         A28 Trevor Hill Street, Newry                                                     
•         A27 Kildare Street, Newry                                                            
•         A2 Sugar Island, Newry                                                                 
•         A28 Upper Water Street, Newry                                               
•         C371 Old Warrenpoint Road, Newry                                        
•         B50082 Cloghoge Road, Newry                                                
•         U6285 The Glen, Newry                                                                
•         U6403 Well Road, Warrenpoint                                                  
•         C371 Greenan Road, Burren                                                        
•         U6104 Ryan Road, Mayobridge                                                  
•         U6070 Ballykeel Road, Hilltown                                                  
•         U6007 Ballyblaugh Road, Mayobridge                                     
•         U6013 Ardkeeran Road, Shinn                                                    
•         U5033 Creggan West Road, Whitecross                                  
•         U5215 Polkone Road, Silverbridge                                            
•         U6077 Cloghanrammer                                                                  
•         U5197 Upper Seafin Road, Killeavey                                        
•         U5216 Garveys Road, Dorsey                                         

Expressing her concern Newry and Armagh MLA Liz Kimmins said “Our roads are already a disgrace, the last thing they needed was a year without proper resurfacing investment. A £120 million resurfacing budget has now been cut down to 80 million because these council areas cannot go ahead with works."

Kimmins concluded “It's vital that these barriers are addressed and the Department gets badly needed investment where it needs to go ASAP".

Loading comment... The comment will be refreshed after 00:00.
Say something here...
or post as a guest

LATEST PHOTOS

Launch of the Rural Heritage of South Armagh Project in Cullyhanna
Monday, 05 October 2026
Launch of the Rural Heritage of South Armagh Project in Cullyhanna
Images: 9
Hits: 254
Greater Newry Business Awards 2026
Sunday, 27 September 2026
Greater Newry Business Awards 2026
Images: 24
Hits: 353
Newry Mela
Tuesday, 08 September 2026
Newry Mela
Images: 20
Hits: 375
Royal Black Institution Black Saturday parade in Newry
Sunday, 30 August 2026
Royal Black Institution Black Saturday parade in Newry
Images: 185
Hits: 3573
Newry Pride 2026
Monday, 24 August 2026
Newry Pride 2026
Images: 91
Hits: 1706

EVENTS CALENDAR

October   2026
M T W T F S S
      1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31  
   
0
Shares