A £150,000 road improvement scheme has been announced for the Kingsmill Road, Whitecross.
The works will enhance the safety of the junction of the Kingsmills and Drumnahunshin Roads by improving junction visibility and forward visibility on the Kingsmill Road.
The work will involve removing a crest on the Kingsmill Road close to the junction. The road will also be widened and a verge will be provided along the length of the scheme. Three hundred metres of road will be resurfaced on conclusion of these necessary works.
It will take approximately eight weeks to complete and to ensure the safety of road users and contractors, it will be necessary to close the road from 20 February 2017 for a period of seven weeks. Signed diversions will be in operation throughout this time.
TransportNI has carefully programmed the works operations and traffic management arrangements in order to minimise any inconvenience to the public, however motorists should be aware that some delays may be expected and that additional time should be allowed when planning any journeys.